SEATTLE — Lanes will be reduced on Interstate 5 while crews replace broken and cracked concrete panels this weekend during “Revive I-5″ work in South Seattle.
The work will happen in the southbound lanes between Albro Place and mid-Boeing Field. Nearby ramps will stay open.
Lane reductions will start at 11 p.m. on Friday, Mar. 1, and run through 4 a.m. on Monday, Mar. 4.
The schedule follows:
- From 11 p.m. on Friday, Mar. 1, until noon, Saturday, March 2, southbound I-5 will be reduced from five lanes to one right lane.
- From noon on Saturday, Mar. 2, until 4 a.m. on Monday, Mar. 4, southbound I-5 will be reduced from five lanes to two lanes.
The work could be postponed due to heavy rain.